EnergyLegal & Compliance

Do you need a licence for a battery storage system in Albania?

Storage up to 1 MW needs no licence under Albania's Law 59/2026. Above 1 MW a licence applies, and a minister approves new storage up to 5 MW.

General information, as of November 2026. This article summarizes public sources and is not legal advice. Albanian energy law is in transition, secondary legislation is still being adopted, and the answer depends on the specific project. Confirm the position with ERE, the distribution operator and a qualified Albanian lawyer before you commit to a battery.

Usually only above 1 MW. Under Albania's Law No. 59/2026, operating a storage facility is a licensed activity, but operators of up to 1 MW of nominal power are exempt. New storage outside concessions needs ministerial approval up to 5 MW and Council of Ministers approval above that. Batteries owned by active clients are treated more lightly.

What counts as energy storage under Law 59/2026?

Energy storage is the deferral of final use of electricity to a later moment, by physical or chemical means, or its conversion into a storable form and later reconversion. That is the wording of Article 3(14) of Law No. 59/2026 "On the Electricity Sector", which the Albanian text calls depozitim i energjisë. A battery is a clear case, and pumped storage is named in the same definition.

Two related terms:

  • A storage facility (impiant i depozitimit të energjisë) is a site where storage takes place (Article 3(31)).
  • Operation of a storage facility is the activity of running one (Article 3(85)). ERE issues a separate licence for it (Article 40(2)(e)).

The law was adopted on 18 June 2026, promulgated by presidential decree on 30 June 2026, and enters into force 15 days after publication in the Official Gazette (Article 137). Karanović & Partners reports that it entered into force on 15 July 2026, which would mean publication on 30 June, the date of the decree. We could not open the Gazette issue itself, so we treat 15 July 2026 as reported. It is the starting point for every deadline below.

Which batteries need a licence, and which approvals apply?

A licence is needed above 1 MW, and a construction approval applies in two tiers: a minister up to 5 MW and the Council of Ministers above it. The thresholds refer to nominal power in MW, not to stored energy in MWh. This is our reading of the Albanian text, which speaks of "installed capacity of nominal power".

Size (nominal power) Storage licence from ERE Approval to build (not a concession) Source
Up to 1 MW Not required Not required for grid-connected storage Art. 40(8), 52(5)
Above 1 MW up to 5 MW Required, up to 30 years Minister responsible for energy Art. 40(2)(e), 41(1)(a), 52(1)
Above 5 MW Required, up to 30 years Council of Ministers, on the minister's proposal Art. 40(2)(e), 41(1)(a), 52(1)

An exemption from the licence is not an exemption from the rules. Article 40(11) says exempt operators must still follow the market rules and grid codes, and ERE keeps the same powers over them as over licensees. Article 40(4) lets ERE monitor, request information, inspect and fine, whether or not a licence is required.

Other points that apply to the licence:

  • Licence conditions include operational safety and protection of life, property and health (Article 41(1)(c)-(d)).
  • ERE may adopt simplified licensing for storage operators connected to the distribution grid (Article 42(2)). We did not find such rules.
  • Municipalities may hold a storage licence, but not a transmission or aggregation licence (Article 40(5)).

The detailed construction-approval rules are for the Council of Ministers to adopt under Article 52(2), on criteria such as system safety, public health and safety, environment and land use. We found no such decision as of 9 November 2026. Article 134 gives the Council of Ministers and ERE 12 months from entry into force to adopt secondary acts. Projects under a concession follow a separate route.

What if the battery sits behind the meter of a solar system?

A battery owned by an active client is largely outside the licence, and it is the main route for farms, SMEs and municipal buildings. An active client is a final customer, or a group acting together, that consumes or stores electricity produced on its own premises, or sells self-produced electricity, provided this is not its main commercial or professional activity (Article 3(44)).

Article 96(3)(ç) lets active clients own and operate storage "regardless of" the licensing article. Article 96(5)(c) adds that they may not face disproportionate licensing requirements or fees. Article 52(5) takes active clients and grid-connected storage of up to 1 MW out of the ministerial approval. The wording leaves open whether the 1 MW limit also applies to active clients, so ask ERE if your battery is larger.

The opposite case is stand-alone storage run as a business or serving third parties. That is licensed above 1 MW.

Council of Ministers Decision No. 368 of 20 May 2026 covers renewable self-producers connected to the distribution grid. It says three things about batteries:

  • A self-producer may consume, store and manage the energy it produces (Article 3(2)(b)).
  • Before commissioning, the self-producer must notify OSSH sh.a. in writing, with manuals and datasheets for all installed products, batteries included (Article 5(10)(a)).
  • Renewable self-production is capped at 500 kW installed (Article 4(1)).

Decision 368 says nothing about storage licensing, charging a battery from the grid, battery size or network charges. Our guide to net billing for solar owners in Albania explains the compensation scheme in that decision. The wider context is in Albania's energy rules in 2026.

Did existing batteries have to register, and by when?

Yes, storage operating or in development without a licence on the date of entry into force had to register with ERE within 60 days. Article 51(3) recognises such facilities and lets them continue, Article 51(5) requires notification and registration within 60 days, and Article 51(4) requires a licence application within 12 months of entry into force.

If entry into force was 15 July 2026, the dates are:

Step Basis Calendar date (our count)
Register with ERE 60 days, Art. 51(5) 13 September 2026
Apply for a storage licence 12 months, Art. 51(4) about 15 July 2027

The assumption is that day one is 16 July, so the 60th day is 13 September. Counting conventions could move either date by a day. As of 9 November 2026, the registration deadline passed 57 days ago, and about 248 days remain to the licence deadline.

What ERE has published:

  • A notice that registration is under Article 51(3) and (5), by post or by email to erealb@ere.gov.al.
  • Board Decision No. 230 of 18 August 2026, with registration rules and a form. It asks for technology, nominal charge and discharge power in MW, storage energy in MWh, grid connection and whether the unit is stand-alone or part of a generation plant.
  • A statement that registration is for record purposes. It is not a licence and does not prejudge the licensing decision (Decision 230, Article 8).
  • Reuse of data already filed with ERE, so operators need not resubmit it (Article 5 of the rules).

On 28 August 2026, ERE amended four solar plants' generation licences to recognise declared storage, repeating the 12-month duty to apply for a storage licence.

One gap: the law's transition text and ERE's notice carry no size limit. Article 40(8) exempts storage up to 1 MW from the licence, but we found nothing saying whether an existing unlicensed battery of that size must also register. Ask ERE in writing.

How do network charges and grid connection apply to storage?

Storage must pay network tariffs approved by ERE, but active clients are protected from double charging. Storage operators have the right to access transmission and distribution networks while paying the approved tariffs (Article 57(1)). Article 21(2) says tariffs must not favour or penalise storage beyond what costs justify.

For an active client with storage, Article 96 adds:

  • A right to connection within a reasonable time, provided the balancing responsibility and proper metering are in place (96(5)(a)).
  • No double charging, including network tariffs, for stored electricity that stays on the premises or is used for flexibility services to system operators (96(5)(b)).
  • Network tariffs calculated separately for energy injected and energy drawn (96(3)(dh)), and financial responsibility for the imbalances the client causes (96(3)(e)).

Article 96(4) adds that after 31 December 2026 active clients may not join self-production schemes that lack separate accounting of injected and consumed energy. We did not verify tariff levels, connection charges for storage or OSSH's technical conditions for batteries.

What should a farm, SME or municipality ask ERE and OSSH?

Ask in writing, state the capacity in MW and MWh, and keep the replies. These questions settle most open points:

  1. To ERE: Does my project count as an active client, and is a storage licence required for my size and use?
  2. To ERE: If I own an existing battery of up to 1 MW that was unlicensed on 15 July 2026, must I be registered?
  3. To ERE: Which licensing rules and forms apply to new storage, and is a simplified procedure available?
  4. To the Ministry of Infrastructure and Energy: Does my project need ministerial approval, and have the Article 52(2) rules been adopted?
  5. To OSSH sh.a.: What are the technical conditions, metering and protection settings for a battery at my connection point, and may it charge from the grid?
  6. To OSSH sh.a.: How are network charges applied to energy that I store and use on site?

Safety and fire rules are a separate question. We did not find Albanian fire-code rules for battery systems and will not guess them. Article 51(6) requires storage operators to meet all applicable legal, technical, safety and operational standards, and Article 41(1) makes operational safety a licence condition. For equipment, our article on LiFePO4 and NMC batteries lists the test reports to ask for and explains why the installation location, ventilation and fire detection must be confirmed with the authority and the insurer. For the engineering side, see sizing solar and storage.

What could we not verify?

Several points remain open and need an answer from ERE or a lawyer.

  • Secondary legislation. We found the ERE registration rules (Decision 230). We did not find the Council of Ministers rules under Article 52(2), the active-client decision under Article 96(2), or ERE's final licensing rules for storage.
  • Gazette date. The publication date, and therefore the 15 July 2026 entry into force and every deadline, is reported, not confirmed from the Gazette.
  • Deadline counting. The 13 September 2026 and 15 July 2027 dates are our calculation. Karanović & Partners writes that the licence application is due "within the following twelve months", which can be read as 12 months after registration. The law text and ERE count 12 months from entry into force, and we follow them.
  • The 1 MW cases. Whether existing unlicensed storage up to 1 MW must register, and whether the 1 MW limit in Article 52(5) applies to active clients.
  • Licence forms and fees. We saw the registration form, not the licence application forms, fees or timelines.
  • Safety rules. Albanian fire and building requirements for batteries.

Confirm each point in writing before you order equipment.

Frequently asked questions

Do I need a licence for a battery storage system in Albania?

Only if its nominal power is above 1 MW. Under Law No. 59/2026, operating an energy storage facility is a licensed activity, but operators with up to 1 MW are exempt from the licence (Article 40). The exempt operator must still follow market rules and grid codes, and ERE can still monitor it. Above 1 MW, an ERE storage licence of up to 30 years applies.

Does a battery behind my solar meter need a licence in Albania?

Probably not, if you qualify as an active client. Law No. 59/2026 (Article 96) lets active clients own and operate storage regardless of the licensing article. An active client consumes, stores or sells self-produced electricity, and this is not its main business. Council of Ministers Decision No. 368 lets renewable self-producers store energy. Confirm your status with ERE before you buy.

Who approves a battery storage project of 1 to 5 MW in Albania?

The minister responsible for energy approves new storage up to 5 MW of nominal power that is not under a concession (Article 52 of Law No. 59/2026). Storage above 5 MW goes to the Council of Ministers on the minister's proposal. Storage connected to the grid with up to 1 MW is excluded from this approval. The detailed procedure is still to be adopted by the Council of Ministers.

Did existing batteries have to register with ERE, and by when?

Yes, if they were operating or in development without a licence on 15 July 2026. Article 51 of Law No. 59/2026 required notification and registration with ERE within 60 days of entry into force, which on our count ended on 13 September 2026. A licence application is due within 12 months of entry into force, so by about 15 July 2027.

How long does an energy storage licence last in Albania?

Up to 30 years. Article 41 of Law No. 59/2026 sets 30 years as the maximum validity of licences for generation, storage operation, aggregation, transmission and distribution. ERE sets the actual conditions and procedure, and Article 42 lets it adopt simplified licensing for storage operators connected to the distribution grid. We did not find the final storage licensing rules.

Do batteries pay network charges twice in Albania?

Not for active clients. Article 96 of Law No. 59/2026 says an active client that owns storage is not subject to double charging, including network tariffs, for stored electricity that stays on its premises or serves flexibility services to system operators. Other storage operators pay the network tariffs approved by ERE (Article 57). The tariff levels themselves were not verified.

Sources

  1. Parliament of Albania: Law No. 59/2026 on the Electricity Sector (2026), text published by ERE
  2. Council of Ministers of Albania: Decision No. 368 of 20 May 2026 on self-producers and net billing (2026), published by ERE
  3. ERE: Decision No. 230 of 18 August 2026 and rules for registering storage facilities in the transitional regime (2026)
  4. ERE: Notice on registering storage facility operators (2026)
  5. ERE: Notice of the Board meeting of 28 August 2026
  6. Karanović & Partners: Albania adopts new electricity sector law (2026)

Contact

Let’s build the future, sustainably.

Whether you’re a business, municipality, or investor, we’re here to help you design and implement smarter, greener systems. Reach out to explore collaboration, partnership, or project opportunities with Greecon.

Email:
info@greecon.earth
Phone:
+355 69 444 3362
Location:
Shijak, Durrës, Albania
By sector:
energy@greecon.earth · agriculture@greecon.earth · water@greecon.earth