EnergyLegal & Compliance

How to connect rooftop solar to the grid in Albania, step by step

Apply to the distribution operator OSSH, build within nine months, fit the meters and notify before energizing. The steps, deadlines and gaps in the rules.

General information, as of 2 November 2026. This article summarizes public sources and is not legal advice. The rules are new, implementing acts are still being issued, and we have not seen the distribution operator's forms or application portal. We separate what Council of Ministers Decision 368 says from what practice may differ. Confirm the procedure for your site with the distribution operator, the Energy Regulatory Entity (ERE), and a qualified Albanian lawyer.

To connect a rooftop or small ground-mounted solar system in Albania as a self-producer, apply to the distribution operator OSSH sh.a. and wait for written approval. Then build and fit the meters within nine months, and notify OSSH in writing, with equipment documents, before switching on. Decision 368 of the Council of Ministers sets this frame.

This guide covers procedure, documents, timelines and metering. For prices, credits and dates, see our guide to net billing for Albanian solar owners.

Who can connect as a self-producer, and what are the limits?

A self-producer is a customer that generates renewable electricity for its own consumption and may store or sell the surplus, as long as this is not its main business (Law 24/2023). Decision 368 (Art. 3) lets any household or non-household customer connected to the distribution grid become one. The decision does not distinguish roofs from ground-mounted systems, so both are covered if the limits below are met. The document list speaks of a building, so ask OSSH what proof it accepts for a field site.

  • Size: 500 kW maximum installed capacity, and no more than the capacity OSSH approves for the connection (Art. 4).
  • Sizing rule: expected annual output must not exceed average annual consumption over the last two years. Where no data exists, a certified energy auditor's report replaces it (Art. 4).
  • Growth: an owner may apply for more capacity if consumption rises, still within 500 kW (Art. 4).
  • Licence: Law 59/2026 (Art. 40) exempts grid-connected producers, including active clients, up to 1 MW from a generation licence.

Our article on sizing solar and storage shows how to match capacity to load. Land and permit rules are outside this decision; see what to check in Albania's 2026 energy law.

What are the steps from application to energizing?

The procedure has seven steps, and the decision sets firm numbers for only some of them. Decision 368 sends most timing questions to ERE's connection regulation, so the table shows where the decision is silent.

Step Who acts Deadline Source
1. Check size and consumption limits Owner None Decision 368, Art. 4
2. File the application (portal, or the regulation's form until the portal exists) Owner to OSSH OSSH portal due within 6 months of the rules' approval Art. 5(1)-(2)
3. Completeness check; OSSH asks for missing documents OSSH 10 working days from the application Art. 5(3)
4. Technical review; written approval or refusal with reasons OSSH Per the connection regulation; none in the decision Art. 5(3), 5(5)
5. Build the plant and install both meters Owner 9 months from approval; one extension of up to half Art. 5(4), 5(9)
6. Written notice to OSSH with equipment documents Owner Before commissioning Art. 5(9)-(10)
7. OSSH energizes and registers the plant OSSH None in the decision; registry within 1 year Art. 5, 10

Three points sit behind the table.

  1. Approval starts the clock. The nine months run from the date the application is approved, not from the date you file.
  2. Failure resets everything. If the plant is not built in time, the owner may ask once for an extension of no more than half the original period, so up to four and a half months. After that the application is cancelled and must be repeated from the start (Art. 5(9)).
  3. The operator can check the build. OSSH may disconnect a plant it finds installed or operating differently from the approved design. It must give written notice, and it may cut access if the owner has not made the corrections within 30 days (Art. 5(11)). The decision's wording about a three-month period in that article is unclear.

For the connection itself, Law 24/2023 (Art. 18) says the operator proposes the most favorable connection point and makes a binding offer within the Distribution Code's deadlines. The same article says self-producer units of 10.8 kW or less, or equivalent connections other than three-phase, are connected after a notification to the operator. We could not confirm how that fits the application procedure.

Which documents does the application need?

Decision 368 lists no application documents, so they come from ERE's connection regulation. The 2024 text of that regulation (Annex III) sets three bands for solar self-producers: 0-10, 11-50 and 51-500 kWp. In every band it asks for:

  • a written request and your ID;
  • a declaration of average annual consumption over the last two years, or an energy-audit report with a proposed capacity;
  • a technical report and equipment manuals and datasheets;
  • a proposal for the two-way meter model and its specifications;
  • proof of ownership of the building where the plant will be built, and an existing supply contract number with no debt (the 0-50 kWp bands say the contract power should match the plant);
  • the designer's licence.

Above 10 kWp, the regulation also asks for a grid-connection project approved by licensed persons, plus data on the main inverter and the production meter. In the 51-500 kWp band it adds a municipal permit for works carried out on prior declaration. All documents must be originals or notarized copies, and OSSH may ask for more (Part 3.7).

Annex III also lists a commissioning certificate signed by licensed designers and contractors, which is odd for an application filed before building. We report it as written; ask OSSH what it expects.

Before commissioning, Decision 368 (Art. 5(10)) separately requires notice with manuals and datasheets for panels, inverters, batteries and meters, data for the operator's registry, and anything else OSSH clearly requests.

What are the metering requirements?

The owner must install two meters at its own cost. Decision 368 (Art. 5(4)) requires a two-way smart meter that measures energy drawn from the grid and energy injected into it. It also requires a one-way meter after the main inverter that measures the plant's production. OSSH sets the technical requirements for both, in line with the Metering Code.

We could not open the Metering Code or the Distribution Code, so we cannot state meter class or communication requirements. The 2024 connection regulation (Part 4.14) adds a practical warning. For new energy sources, metering must meet OSSH's technical criteria, and a system installed without OSSH approval is not treated as regular and will not be sealed. Confirm the meter model with OSSH before buying.

Who pays for what?

The owner bears the connection and metering costs. Law 24/2023 (Art. 19) puts connection and metering equipment on the producer and reinforcement of the wider network on the operator. Law 59/2026 (Art. 31) says the applicant covers the full cost of a connection, and that extra network upgrades can be agreed at the applicant's cost with ERE approval. If OSSH refuses an application for technical reasons, the owner may offer to pay for a network improvement (Decision 368, Art. 5(7)).

The 2024 regulation has a fee annex for solar self-producers up to 500 kWp. It sets a study fee of 1,000 lek for households, 5,000 lek for low-voltage non-household customers and 23,000 lek for medium voltage, no distance or power fee, and a services fee that includes meter verification. Section 4.12 of the same regulation gives different figures for generation sources in general, so ask OSSH which applies. These are 2024 figures.

How do apartment buildings and shared systems work?

Self-producers in the same building, including multi-apartment blocks, may act jointly and organize sharing of the energy produced there (Decision 368, Art. 3(3); Law 24/2023, Art. 20). The sharing must respect network tariffs, other tariffs and taxes.

The decision does not say how a joint application is filed, who holds the supply contract, how meters are arranged or how energy is split. Law 59/2026 (Art. 40) exempts energy sharing from a supply licence only after ERE sets maximum price terms and the sharing entity notifies ERE. We did not find such an ERE decision. If a third party owns or runs the plant, Law 24/2023 (Art. 20(5)) says it must stay under the self-producer's instructions and is not itself a self-producer. Our post on contracting connected infrastructure covers allocating these risks.

What can go wrong?

Most problems come from missed deadlines and mismatched documents. The texts point to these cases.

  • Incomplete file. OSSH has 10 working days to ask for missing items. It will not approve a request if the applicant owes OSSH money or has not met technical conditions (regulation, Part 1.5).
  • Technical refusal. OSSH must refuse a design that breaches the Distribution Code or cannot keep frequency and voltage within limits at your point. It must give written reasons. You can complain to OSSH and ERE, or reapply (Art. 5(5)-(7)).
  • Oversizing. Output above average consumption, or capacity above what OSSH approves, breaks the sizing rule (Art. 4).
  • Missed payment windows. The 2024 regulation voids an offer if the applicant misses short payment deadlines, for example 7 working days for small low-voltage connections and 10 calendar days for generation sources.
  • Missed build deadline. Nine months, one extension, then a fresh application.
  • Build differs from design. Disconnection can follow, with 30 days to correct.
  • Wrong meter. An unapproved meter will not be sealed.
  • Moving rules. Existing owners are due to move to net billing once ERE approves a price. That changes the economics, not these steps.

What is not yet in force, published or confirmed?

Decision 368 enters into force on publication in the Official Gazette. We did not find that issue, so we cannot date its deadlines. The six-month portal deadline counts from "approval" in Art. 5(2), while other deadlines (Art. 5(12)-(13), Art. 10) count from entry into force. Counted from 20 May 2026, the portal deadline falls on 20 November 2026. Counted from publication, it falls later.

As of 2 November 2026, we found none of the following:

  • an OSSH online portal for self-producers; a September 2026 report describes an OSSH tender for automating applications and approvals;
  • an ERE decision amending the connection regulation (simplified self-producer procedures, due as an OSSH proposal within three months of entry into force), the Distribution Code or the Metering Code (six months); the ERE register we checked runs to 8 October 2026;
  • the operator's real-time registry, due within one year;
  • operator forms and a current document checklist; the OSHEE self-producer page we opened still cites older law and does not mention Decision 368.

Treat the 2024 regulation as the latest text we could read, not as confirmed practice. Confirm rules and forms before you order equipment or sign a contract.

Frequently asked questions

How do I connect a rooftop solar system to the grid in Albania?

You apply to the distribution operator, OSSH sh.a., and wait for its written approval. Then you build within nine months, install a two-way smart meter and a production meter at your cost, and notify OSSH in writing with equipment documents before commissioning. Decision 368 sets this frame; the application form and documents come from ERE's connection regulation.

How long does it take to connect a solar self-producer in Albania?

No total time is fixed in Decision 368. It says OSSH reviews the application within the deadlines of the ERE connection regulation and flags missing documents within 10 working days. The owner then has nine months to build. The 2024 regulation text gives, for example, up to 20 working days for a low-voltage connection up to 20 kW. Which timeline applies to your system is unconfirmed.

What documents do I need to apply for a solar self-producer connection in Albania?

Decision 368 does not list them. The 2024 text of ERE's connection regulation lists, for all sizes, a request, a consumption declaration or energy audit, a technical report, equipment datasheets, ID, proof of ownership and a meter proposal. Systems above 10 kWp also need an approved grid-connection project, and systems of 51-500 kWp need a municipal permit. Confirm the current list with OSSH.

Do I need a licence to run a small solar plant in Albania?

Usually not a generation licence. Law 59/2026 exempts producers, including active clients, connected to the grid with installed capacity up to 1 MW from the generation licence. A self-producer is capped at 500 kW under Decision 368, so it falls within that exemption. Grid approval from OSSH, building-related permits and other duties still apply.

Who pays for the meter and the grid connection?

The owner pays. Decision 368 requires the self-producer to install the smart meter and the production meter at its own cost, and Law 59/2026 puts the full cost of a grid connection on the applicant. The 2024 regulation lists small fees for self-producers up to 500 kWp, such as 1,000 lek for a household study fee. Confirm current amounts with OSSH.

Can an apartment building share one solar system in Albania?

Yes, in principle. Decision 368 lets self-producers in the same building, including multi-apartment blocks, act jointly and organize sharing of the energy produced there, while respecting network tariffs, other tariffs and taxes. The decision gives no procedure, metering layout or sharing method for this, so ask OSSH how a joint application and the meters would be handled.

Sources

  1. Council of Ministers: Decision No. 368 of 20.5.2026 on connection rules and the net-billing compensation scheme for renewable self-producers (2026)
  2. Albanian Parliament / ERE: Law No. 24/2023 On promoting the use of energy from renewable sources (2023)
  3. Albanian Parliament / ERE: Law No. 59/2026 On the Electricity Sector (2026)
  4. ERE: Regulation on new connections in the distribution system, text amended by Board Decision No. 145 of 19.07.2024 (2024)
  5. ERE: Board decisions 2026 (register, newest entry 8 October 2026)
  6. Monitor: Rritja e fotovoltaikëve, OSSH studim për investimet në rrjetin e shpërndarjes sipas nevojës (2026)
  7. OSHEE: Vetëprodhuesit (self-producers page, undated)

Contact

Let’s build the future, sustainably.

Whether you’re a business, municipality, or investor, we’re here to help you design and implement smarter, greener systems. Reach out to explore collaboration, partnership, or project opportunities with Greecon.

Email:
info@greecon.earth
Phone:
+355 69 444 3362
Location:
Shijak, Durrës, Albania
By sector:
energy@greecon.earth · agriculture@greecon.earth · water@greecon.earth